Check list used when performing a test case
When executing a test case which is verifying a function, interference, fault situation etc. in TelORB some steps always has to be done before, during and after the test to ensure that the system is behaving as it should.
Here is a list of what to do. To see more information about each step, click on the item.
To do before the test case
- Remove all error dumps
- Check Alarms and Notifications
- Check statistics for Demo2000
- Check the processor load
- Prepare the syslog
To do during the test case
- Look for error dumps
- Look for Alarms and Notifications
- Monitor the processor load
- Look for messages in the syslog
- Check the console logs
To do after the test case
- Analyse all received error dumps
- Analyse all unexpected Alarms and Notifications
- Check statistics for Demo2000
- Check the processor load
- Analyse messages in the syslog
- Redo the test without faulty situations
- Mark the test case/trouble report as "tested", if OK
2001-05-16 Andreas Johansson